PACEMD
Active Member
Turns out that the transformer I showed is for the truck stop not the superchargers. So I was indeed wrong. The supercharger transformer will go on the platform on the left but is not yet installed. I posted new pictures on the Miles City supercharger post. The new work began on 2/17/20. Charging stands may be installed as early as tomorrow and transformer installed and energized as early as next week, or not. The electrician thinks the site to the west will be Forsyth, not Bighorn.