So long as there is no big delay in getting the utility transformer installed and everything energized, then it should certainly be operational before year end. When talking to planning/zoning boards, Tesla says that they generally expect the construction phase to last 3 to 6 weeks. But timing/scheduling with the utility and transformer procurement is always a bit of a crap shoot, so even if they are basically done being built they could end up having to wait months until things are actually finished.Open date still in 2018????
You are da real mvp!Status as of this morning is: they are working on a Saturday, pad and foundation concrete poured and curing, steel post in place for the fencing and large boxes in the enclosure which may be the charging structures (only a guess). Here are a couple of pictures.View attachment 353469
More likely the surround for the transformers, chargers and perhaps battery pack.What are the vertical beams? Support for a roof/cover? I kind of hope not, because that will tempt ICE vehicles to park there.
I was wondering the same...Anything happening in the past week since the pictures above were posted? I keep this page bookmarked and check it every day.