I was at Broadway Plaza Monday (4 days ago) and went by the new Sales office location. I chatted up the general contractor who was up to his ears in subs (crawling over each other to finish up). The floor has been laid, walls done, electrician hanging light fixtures, casework just delivered. He is scheduled to turn over the store to TM on Mon.4/21. TM still needs to install 'trade dress', displays, computers, telephony, networking, furniture, plus 1 chassis and 1 Model S. The expected 'go live' date is on or about May 1st.
The 6 HPWCs are being installed in the garage on the first floor (was part of the employee parking area). The floor has been epoxy painted and red striping applied to the floor and walls. The electricians were to hang new lighting this week and install the HPWCs. He expects that this will be ready next Monday as well (but likely not available to us before the store actually opens).
As far as the Service Center, no new activity at the N. Main Street location.
BTW, I was out at the Corte Madera Sales center (Village @ Corte Madera). Their permanent larger location in the mall is expected to 'go live' on May 1st as well, with room for a chassis and 2 Model S. The 6 HPWCs are around back and run at 208V 72A (due to the mall's infrastructure). If the spaces are full, park somewhere and go into the store and ask for Brian or another sales team member and they can move a test drive car to free up a space.