I was wondering if this would be using the pre-fab units, but there are 5 of these power cabinets on-site already.

I was wondering if this would be using the pre-fab units, but there are 5 of these power cabinets on-site already.
These appear to be the 5 switch boxes. Each switch powers 4 stalls. Looks like a hard install of at least V3.
 
  • Like
Reactions: iCAR
This looks like the transformer base with underground cable access ports. It’s on the SE side of the parking lot, and maybe the 20 pedestals will all be in the middle of the previous parking spots, on the left side in this picture.
 

Attachments

  • IMG_4535.jpeg
    IMG_4535.jpeg
    1,000.1 KB · Views: 17
  • Like
Reactions: RickParker
Another Bird day (little icy, but good) and stopped in again on my way home. Again not much change overall but they made a lot of progress on that cement vault hole. Tons of new piping coming out of the vault. In my night pics above, the second one, that whole area next to where the PVC pipes stick out is now all filled with additional piping. Huge amount of conduit. They were still working about 5:30pm when I went by so I didn't take any pics.

Also noticed most of the worker trucks had Montana plates.

Finally as a unrelated heads up, Bird is closing Mineral at 3, Little Cloud at 3:30 now. They will close even earlier starting next weekend.
 
  • Informative
Reactions: Krash
Another pow day in LCC, and on the way back stopped in again... The recent storm has unearthed that this will be a V4 charger location! Also the water is gone from the trench. No apparent change though, I think the snow scared off the workers for a few days. Photo's from around 4:30PM 5/9/24.
IMG_8170.jpeg


IMG_8171.jpeg

IMG_8172.jpeg

IMG_8174.jpeg



/edit. Hey @corywright, @Big Earl, or @paulkva , can we adjust supercharge.info to show 20 V4 instead of V3?
 
Last edited:
Sunday is good time to see the activity, no one was there. Here’s the equipment labels - 5 ea V3.5 Switch Boxes
-20 ea SC Post, V4, NACS W MD(Magic Dock?)
It appears there will be 10 parking spots back to back, with the row of existing spots on the N edge of the lot remaining open. This will allow snow removal on both sides of the posts in the middle of the lot. The 5 switch boxes will be together next to the transformer pad.
With good weather in the forecast maybe we’ll see more activity fast.