Some info for reference:
Abbotsford SC took about 2 weeks from the fence going on to be activated, and was on the navigation after ~4 days of being on (mar 2020).
West Kelowna finished construction Dec 23, 2020, but wasn't activated until Mar 4, 2021.
So it could be a while. Last time I was there I didn't see the bchydro transformer pad, so I think that work is still outstanding