Progress is being made here in Bozeman, MT. This SC will take 4 weeks instead of just 3 weeks due to a transformer delivery delay. Construction started September 5, 2014 so a Possible opening approximately Oct 3, 2014. This was taken Friday September 12, 2014.
Progress is being made here in Bozeman, MT. This SC will take 4 weeks instead of just 3 weeks due to a transformer delivery delay. Construction started September 5, 2014 so a Possible opening approximately Oct 3, 2014. This was taken Friday September 12, 2014.
Great news! Thanks so much for the update. I am indeed coming through right around that time. I will probably be too early on my outbound trip (~Sep 28), but when I return around Oct. 10-11, hopefully I will be an early user! Hoping I can stop by your place, DrGuest, on the outbound trip for charge. :smile:
There's a talk at the university about electric vehicles on the evening of Oct 15 that I hope to catch if the chargers are up and running. Being put on by a Jackson group. I can get details if it's not readily discerned.
Bighorn is it the "Yellowstone - Teton Clean Energy Coalition" ? They are a group that got Jackson Hole, WY some 30 amp chargers for free in there downtown. I've shared an Idea with them I had for getting a reduced price (free) for Ev's entering our National Parks and a fast lane, to help cut down emissions in some of our most sensitive habitats, Like Yellowstone and Tetons.