The intent of the ≤ symbol is to indicate the possibility that the location might not deliver the full power as indicated on supercharge.info. The primary case was meant for sites with a mix of stall types, for example some sites like Woodbridge NJ have a mix of V2 and V3 stalls, so depending on where you plug in, you might only be able to get 150 kW max instead of the 250 kW listed for the site. I mentioned that in another thread earlier this week.

Also noted in the other thread: there's a bug in the logic where a site that has a single stall type but multiple plug types (like MagicDock or dual-cable stalls) will show the ≤ symbol even though the max power is the same at every stall. Hoping to fix that soon.
 
Pardon my ignorance but why does the supercharge.info site show less than or equal to 250 kW? Shouldn't it be greater than or equal to 250 kW?
A discussion on said topic can be found here. (Yes odd place for that discussion, but the answer is there.)

/edit. Hey @bmah can we get the "permit" part of the thread title removed since this is now under construction? I think just "Supercharger - Farr West UT" will work.
 
Last edited:
IMG_4656.jpegIMG_4653.jpegIMG_4657.jpeg

Based on my update
on the Park City SC today and pictures of the equipment labels on-site, these pre-fab units at Farr West may be the same -
V3.5 Switch Cabinets and V4 SC Posts NACS W MD?
 
Good Progress today with the 4th Supercharger Cabinet moved over next to the switching box cabinet. The meter box is mounted, but the working crew said it was installed on the incorrect side and will have to be moved to the west side. The transformer pad is installed and the entire area has been leveled and drainage grills installed.
Pads have yet to be installed for the extra Two Charging Posts that the plans show will be between the two prefab units to service the handicap stalls.
Stopped by the Farr West site today and it looks pretty much the same as in the pictures from May 3. Still needs some blacktop and a utility transformer. :(

Picture from this morning.
IMG_1233.jpeg
 
Interesting they are so far apart.

Also going to politely ask again: Hey @bmah, as this site is clearly under construction could you remove "permit" from the thread title? Pretty please? 😀

Done, although for future reference, it's really better to do a report on a post in the thread rather than tag a specific moderator.

Bruce.