You can install our site as a web app on your iOS device by utilizing the Add to Home Screen feature in Safari. Please see this thread for more details on this.
Note: This feature may not be available in some browsers.
1334 Saratoga Ave, San Jose.
Under construction. Couldn't find permit with city of San Jose though... *shrug*.
This center also already has Electrify America stations.
Agreed. That lot is kinda small. Westgate would have been a much better location. Nonetheless, there are lots of apartment buildings nearby with many potential Tesla owners. As if there weren't enough Teslas on the roads around here already...
Good! I stopped by there a couple days ago and the construction fencing was still up. There is a three stall EA station on the other side of the parking lot to the right of your photo. Two were in use.
Still think they should have put a bigger station at nearby Westgate Mall.
An interesting aspect of this site is that only four stalls have the traditional "back in" style stall positions. The other eight stalls have the charging stands set outwards as shown in the previous posts' photo. Maybe better for eventual CCS support?
June 4th and still waiting for PG&E to energize. Anyone know what's the hold-up? Someone mentioned "transformer" - that could take them months. I'm happy, it's very close to me. Although I mostly charge at home.
June 4th and still waiting for PG&E to energize. Anyone know what's the hold-up? Someone mentioned "transformer" - that could take them months. I'm happy, it's very close to me. Although I mostly charge at home.
July 11 -still no love... The chargers are just sitting there looking sad. Where can we get any information? More than two months since hard construction was completed.
July 11 -still no love... The chargers are just sitting there looking sad.
Where can we get any information? More than two months since hard construction was completed.
July 11 -still no love... The chargers are just sitting there looking sad. Where can we get any information? More than two months since hard construction was completed.
This one is looking to be like another Burbank story (I hope not tho). Baby Burbank (8 V3 stalls-construction was finished back in December and up to this date, still waiting on the transformer/Burbank Water and Power.
These cases, I assume is because some major power transfer/routing of cables-power to the supercharger area needs to be done or something in that matter.