PXL_20240224_200117113.jpgPXL_20240224_200104713.jpgPXL_20240224_200102341.jpgPXL_20240224_195945162.jpgPXL_20240224_195909090.jpgPXL_20240224_195856898.jpgPXL_20240224_195853836.jpg

The video screen frame is up!
 
Last edited:
Not too far from done though either. The main building is mostly complete and they just need to work interiors and they have already run conduits for the Supercharger cabinets and stalls. Still has at least a couple of months to go, but probably open sometime this summer.

Progress as of April 12th thanks to 247 Tesla's YouTube channel. The conduit was laid about a week prior to this and in this video it is getting covered with concrete.

1713389336594.png


1713389395359.png


Full Video:
 
Not too far from done though either. The main building is mostly complete and they just need to work interiors and they have already run conduits for the Supercharger cabinets and stalls. Still has at least a couple of months to go, but probably open sometime this summer.

Progress as of April 12th thanks to 247 Tesla's YouTube channel. The conduit was laid about a week prior to this and in this video it is getting covered with concrete.

View attachment 1039437

View attachment 1039438

Full Video:
Ohhhhh niceeee. Its moving fast.
 
  • Love
Reactions: zoomer0056
Not too far from done though either. The main building is mostly complete and they just need to work interiors and they have already run conduits for the Supercharger cabinets and stalls. Still has at least a couple of months to go, but probably open sometime this summer.

Progress as of April 12th thanks to 247 Tesla's YouTube channel. The conduit was laid about a week prior to this and in this video it is getting covered with concrete.


Full Video:
I haven’t seen the last video, but is that Elon and does he say “two weeks”


Too soon?
 
I drove by this building on the way to Netflix Is A Joke on Sunday. It looked small from the street... now I know this is because there's another lot connected to it by a small gap between the 2 other buildings. The red building really needs to go.
 
Not too far from done though either. The main building is mostly complete and they just need to work interiors and they have already run conduits for the Supercharger cabinets and stalls. Still has at least a couple of months to go, but probably open sometime this summer.

Progress as of April 12th thanks to 247 Tesla's YouTube channel. The conduit was laid about a week prior to this and in this video it is getting covered with concrete.

View attachment 1039437

View attachment 1039438

Full Video:
I know this is about a month late but following up on whether this is an expansion, it looks like some things have shifted location from the posted plans.


It looks like the termination of many conduits are behind the neighboring building on the other lot. It almost looks like there is room to drive through but on the most recent picture, the conduit they were covering in cement is completely buried so it is hard to tell if the sites are just connected for staging or if they will be connected long term.