Last I heard from someone who was down at the site, was the goal was to have NStar hook up power by mid-August. A couple weeks past that goal and the pole is now up. Can't imagine it will take them very long to get power from across the street to the Superchargers, just need the man hours from the electrical company. I'm pretty sure the superchargers have been tested (using a generator). No one spotted the Model S down there charging though!
Before the project started the timeline was something like 4-6 weeks from start to finish. Will probably end up being about 3 months. I'm guessing the delay is due to the power company and not Tesla. Hopefully this leads to more level 2 charges around Southeastern MA and Cape Cod.