Omaha's first Supercharger will be located at a Hyvee 8801 WEST CENTER RD. Footing/Foundation permit filed here.
You can install our site as a web app on your iOS device by utilizing the Add to Home Screen feature in Safari. Please see this thread for more details on this.
Note: This feature may not be available in some browsers.
Kearney appears to report permits monthly, so we'll need to keep an eye on that. North Platte does not report permits online. But with the Omaha and Lincoln sites appearing on Tesla's map last week and both getting permits this week I wouldn't be surprised if both of those aren't in progress either.Great first and second posts from yourself and @Mr. Nuke!! Tesla is permitting these new Superchargers in quick succession
Great news. The SC in Council Bluffs is old, sucks and is a pain to get to.Great first and second posts from yourself and @Mr. Nuke!! Tesla is permitting these new Superchargers in quick succession
The permit that is posted says there will be 12 EV signs and the attached Google Map shows there are 12 spots that I highlighted in the upper right of the image. So, we'll see if this is where they will be located.I'm kind of surprised they picked this particular HyVee, it already seems pretty tight on parking as is. I don't shop here regularly but even in mid day the lot is pretty full. As small as the lot is, there is really no "far side of the lot" to place the chargers.
On the other had, if Hy-vee is the charging partner this is seemingly the most logical one for transient I-80 traffic as well as being fairly well centered city wise as well.I'm kind of surprised they picked this particular HyVee, it already seems pretty tight on parking as is. I don't shop here regularly but even in mid day the lot is pretty full. As small as the lot is, there is really no "far side of the lot" to place the chargers.
The permit also specifies the West end of the parking lot. It is seemingly going to go near where AdamY2022 and Trips have observed the survey stakes just South of the Fast and Fresh gas station store.The permit that is posted says there will be 12 EV signs and the attached Google Map shows there are 12 spots that I highlighted in the upper right of the image. So, we'll see if this is where they will be located.
Yeah... this area that you, Trips and AdamY2022 have pointed out seems to be the better option. The one in the northeast is probably too close to the busier West Center road.On the other had, if Hy-vee is the charging partner this is seemingly the most logical one for transient I-80 traffic as well as being fairly well centered city wise as well.
The permit also specifies the West end of the parking lot. It is seemingly going to go near where AdamY2022 and Trips have observed the survey stakes just South of the Fast and Fresh gas station store.