randygts If you are going to Gulf Shores Hotel Magnolia would be just fine. If you are just passing threw try The Battle House in downtown Mobile. Very close to the Entertainment District.
Yea supercharger was on, parking stops were a bit of a pain. Arrived with 70 miles left charged @ 365v 317 amps 356 miles per hour got 140 miles in 30 min. This is the way charging was meant to be.
Alabama Power has schueled and outage for a large shoe store in the wee hours tomorrow to finish connection to 13.8 kv line. Meter dept set meter today. Workers were getting ready to do their last concrete pour around transformer. I think all of the wiring in station & charging stands are done...
jbabb is correct, signs have been installed 1 on this side 7 on the other side faceing south. Crew finish the pour for the curb around transformer. Electricians finish cable pulls inside station, were pulling cables to charging stands this afternoon. Al power doing their thing plus meter dept...
Alabama Power set a 750KVA transformer this morning, they plan to be able to make it hot wed. if everything else is ready. The contractor is still planning on being ready friday.
I am proud to report the high voltage conduit bore went well and the transformer pad had been poured. Station switch gear and charger cabinets have been installed. The out side wood fence was about 1/2 finished. Boss man said that alabama power was going to set transformer Monday. I plan to...
Happy to report they did pour concrete today. Main charger pad all of the stations & sign posts. They plan to bore app. 150 ft to the north to Al Power underground vault on wed. Some one ask where they were going from here and they said that it had been several months since they had been home so...
I really do appreciate all of your kind words. I would like to think that we are doing our part to get people off oil and clean up the environment so we all can breathe easier. I would love to meet all of you kind people.
Went by today and saw 7 crates marker Tesla. 3 were switch gear 4 were chargers. Counted 8 conduit risers for stalls. Worker said they planed to pour concrete Monday be done in 2 weeks. They came from OK. did not know where they were going from here.